원전 차폐 콘크리트 구조물 제염해체공사 리스크 분류체계 구축: 구조적 / 작업 리스크를 중심으로

Development of Risk Breakdown Structure of Nuclear Power Plant Decommissioning Project: Focusing on Structural Damage / Work Process Risks

초록

The purpose of this study is to deduct the structural damage / work process risks factors which can be occurred during the decommissioning in the NPP containment concrete structure. To achieve these purpose, risk profile specified in the construction industry is analyzed, and the work process of NPP decommissioning and the construction project were matched based on the similarity of each works. Accordingly, human and physical risk factors are classified. Finally, the risk associated with the building structure and work process was classified as per their process activities, and risk typology explaining the disaster which put the structure, equipments, machine and workers in serious danger was developed.

키워드

NPP(Nuclear Power Plant); Decommissioning; Dismantling; D&D; Hazard; Risk factor; 원자력발전소; 제염공사; 해체공사; 제염해체공사; 위험요소; 리스크 요인
제목
원전 차폐 콘크리트 구조물 제염해체공사 리스크 분류체계 구축: 구조적 / 작업 리스크를 중심으로
제목 (타언어)
Development of Risk Breakdown Structure of Nuclear Power Plant Decommissioning Project: Focusing on Structural Damage / Work Process Risks
저자
김별; 이주성; 안용한
DOI
10.11112/jksmi.2018.22.3.038
발행일
2018-05
저널명
한국구조물진단유지관리공학회 논문집
권
22
호
3
페이지
38 ~ 45